ASHANTI REGION PROJECTS

Kumasi Road and Drainage Extension Project (KRDEP)

Lake Road Extension, Sissai Drain and ancillary works

KRDEP – Lake Road Bridge launched – Approach fills ongoing but very slow

KRDEP – Coca Cola Junction

The KRDEP is a sequel to the Kumasi Roads and Urban Development Project (KRUDP) which was completed earlier. The project comprised of the following subcomponents

  1. The completion of the Oforikrom to Asokwa Bypass,
  2. The development of the Sokoban Wood Village a purpose-built industrial estate to accommodate the wood workers who were operating within the right of way
  3. The construction of the Lake Road 0 +000 to 6 +500
  4. The construction of the Lake Road Interchange

The KRUDP did not have adequate funds to undertake all the works prepared and as a result the KRDEP was prepared to undertake the outstanding works which comprised mainly of the extension of the lining of the Sisa Stream for another 2.0km and the extension of the Lake Road from Km 2 +700 to about Km 5 + 200

 

To improve travel options and access to and within the southern parts of the Greater Kumasi Metropolitan Area.

 

The scope of works includes the following

– Extension of the Lake Road from K2+540 to K5+200 and its associated works

– Construction of structures including

– The Lake Road Bridge at K4+100,

– S-line vehicular Bridge at Ch. 0+900 and

– S-line footbridge at Ch. 1+020.

– The Extension of the lining of the Sissai Drain by an additional 2 km and 100m of stone pitching.

– Design and supervision of the construction of the extension of Lake Road

– Design and supervision of the construction of the new Atonsu Terminal and about 360m Terminal access road

Employer: Ministry of Roads and Highways 

Contractor: M/S China Henan International Corporation

Consultant: Zutari Ltd/ABP consult Ltd.

Contract Duration: 26 months

Funding Agency: Agence Française de’Developpment (AFD)

The percentage of work completed by the contactor as of March 2023, is 98% as against programmed works of 100%. The contract officially expired on December 31, 2021, but an extension has been requested till the end of July 2022. Breakdown of progress is as follows.

– Lake Road – 99%

– Relocation of Utilities – 99%

– Sissai Drain – 97%

– Lake Road Bridge –  100%

– Vehicle Bridge –  100%

– Foot Bridge –  100%

– Bus Terminal –  100%

Road Furniture 90%

 

Ongoing works consists of installation of streetlights, road line markings and signs, guardrails, and traffic signals.

The contactor is ahead of schedule with achievement at 57%. The contractor is currently working on the Mechanized Stabilized Earth walls and filling for abutment A2. This activity is on-going which has been interrupted by intermittent rainfall.

It should be noted that the submission of the designs on the ground works by QGMI-UK is critical for works to start and to forestall any delays that the rains may cause. Outstanding works to be accomplished include but no limited to fabrication and installation of Precast Planks and main members of the bridge and road works.

 

Reconstruction of Sunyani Road in Kumasi, Phase 2

Dualization of New Bekwai Road

Retaining Wall at Abuakwa

Asphaltic works at Cambridge

The Sunyani Road in Kumasi is part of the National Route 6 (N6), the roads start from Apenkwa on the N1 in the Greater Accra Region and ends in Gonokrom in the Bono Region.

The section of concern is from the Centre for National Culture through the Komfo Anokye Teaching Hospital on to the Bekwai Roundabout through Sofoline Interchange and ends at Abuakwa.

The section of concern is within Greater Kumasi Metropolis and acts as an urban arterial. This section was one of the most congested routes identified in the Kumasi Arterial Roads study undertaken by Messrs. Comptran Engineering and Planning Associates and recommended the dualization and intersection improvement of some junctions.

 

To improve urban mobility and safety in the western corridor of the Greater Kumasi Metropolitan Area

 

The scope of works for the Phase 2 are.

  1. Outstanding works from Phase 1 (Tie-in at Apatrapa junction, 7no. junctions, Pedestrian Underpass structures and accessories and Pedestrian Underpass Street lighting)
  2. Reconstruction of Sunyani Road (SYN 0+000 – SYN 3+500 and SYN 9+200 – SYN 11+000)
  • Dualization of the New Bekwai Road (Bekwai roundabout to Santasi roundabout)
  1. Construction of Interchange at Bekwai roundabout.
  2. Development of selected roads in South Suntreso, Asuoyeboah, Apatrapa and Abuakwa
  3. Relocation of Utility lines along the New Bekwai Road

 

Employer: Ministry of Roads and Highways 

Engineer: The Director, Department of Urban Roads

Contractor: M/S China Geo – Engineering Cooperation

Consultant: ABP Consult Ltd

Contract Duration: 24 months

The percentage of works completed by the Contractor as of June 30th 2023, was 45% as against 70% planned works. Breakdown of physical progress is as follows.

– Outstanding Works from Ph 1 68%

– Sunyani Road   74%

– Tanoso Underpass 94%

– New Bekwai Road 1.0%

– Interchange at Bekwai Rndabt 0.0%

– Dev’t. of Selected Roads 33%

– Utility Relocation 59%

– Pedestrian Underpass at Tanoso 94%

– Miscellaneous Civil Works 44%

Design, Fabrication, Supply & Installation of 50 no’s Czech
Modular Steel Bridges and related Civil Works in Ghana (DUR Components)

Background 

The Department of Urban Roads was allocated ten (10) components of the fifty (50) nos. There are three of them in the Greater Ashanti Region.

 

Objective 

The project aims to provide connectivity of travel to commuters and replace old bridges in the selected area

Afful Nkwanta – Ahwiam over Aboabo (30m)

Afful Nkwanta – Ahwiam over Aboabo river

Employer: Ministry of Roads and Highways 

Engineer: The Director, Department of Urban Roads

Contractor: M/s KNIGHTS A. S.

Sub-Contractor: M/s Billquis Int. Gh. Ltd

Consultant: M/s JIT Investment Ltd

Physical progress achieved by the contractor as of June 2023, is 56%.

Kokoso – Bohyen Road (30m)

Employer: Ministry of Roads and Highways 

Engineer: The Director, Department of Urban Roads

Contractor: M/S KNIGHTS A. S.

Sub-Contractor: M/S Ussuya Ghana Ltd

Consultant: M/S JIT Investment Ltd

Physical progress achieved by the contractor as of December 2022 is 94%.

Susuanso – Anloga over Sisa (30m

Kokoso – Bohyen Road Bridge

Employer: Ministry of Roads and Highways 

Engineer: The Director, Department of Urban Roads

Contractor: M/S KNIGHTS A.S.

Sub-Contractor: M/S B.K Blow Ltd

Consultant: M/S JIT Investment Ltd

Physical progress achieved by the contractor as of December 2022 is 94%.