MAINTENANCE ACHIEVEMENT – JANUARY – JUNE 2021
PERIODIC MAINTENANCE | ROUTINE MAINTENANCE | ||
Activity | Ach/km | Activity | Ach/km |
Gravelling | 114.81 | Grading/Patching | 901.35 |
Partial Recon. | 9.74 | Pothole Patching | 527.36 |
Minor Rehab & Upgrad. | 72.56 | Minor Drain Repairs | 39.85 |
Resealing | 2.33 | Kerb Cleaning | 1,468.07 |
Asphalt Overlay | 243.45 |
MAJOR PROJECTS ONGOING
- ACCRA URBAN TRANSPORT PROJECT – POKUASE INTERCHANGE PROJECT
The specific objective of the Accra Urban Transport Project is to promote efficient movement of goods and people to and from the city through Pokuase, boost trade along the connecting routes, provide income generation opportunities, promote affordable transport services and generally improve the livelihoods of the people in the project area. The project is being funded by the African Development Bank (AfDB) and the Government of Ghana (GoG). Main Works include:
- Construction of a four (4) Tier interchange at Pokuase Junction
- Construction of 10km of selected local roads to connect the communities to the interchange
- Construction of overhead footbridge
Contractor: M/S Zhongmei Eng. Gp. Ltd.
Commencement: 4th April, 2018
Expected Completion: June, 2021
Physical Progress: 99.9%
2. KUMASI ROADS AND DRAINAGE EXTENSION PROJECT
The project is being funded by Agencę Française de’Developpment and is in three main components:
- The expansion of existing Lake Road (single carriageway) into a dual carriageway from Coca-Cola Bottling Company area km2+700 to km4+700; a further extension to Dompoase Junction and thence to the new Terminal at Dompoase.
- The extension of Sissai drain by 2km;
- Construction of 3 No. Reinforced concrete bridges across the Sissai River.
Contractor: M/S China Henan Int. Coop. Group (Gh) Ltd.
Commencement: 1st February, 2019
Expected Completion: December, 2021
Physical Progress: 73.00%
3. LA BEACH ROAD COMPLETION PROJECT
The project seeks to improve the capacity along the Accra Tema Beach Road and ensure the safety of commuters and other road users. This project would go through communities like Osu, La, Teshie, Nungua, Tema Community and Sakumono.
|
LOT 1 |
LOT 2 |
Contractor: |
M/S China Gansu Int. Corp |
M/S China Major Bridge Eng. Co. Ltd |
Commencement: |
June, 2020 |
November, 2020 |
Physical Progress: |
10% |
13% |
4. CONSTRUCTION OF OBETSEBI LAMPTEY INTERCHANGE PH. 2
This project generally seeks to reduce congestion around the Obetsebi roundabout and facilitate the free movement of goods and people. The project also seeks to solve the perennial flooding within the project location by upgrading the existing drainage structures. Works have commenced on the Kaneshie Storm Drain while awaiting approval to commence construction.
Contractor: M/S QGMI
Commencement: –
Expected Completion: –
Physical Progress: 15%
5. TAMALE INTERCHANGE
The Tamale interchange is about one kilometre long and links the Kumasi road through the Point 7 road, the Central Taxi Rank, Central Market intersection with the Melcom Road and Bolgatanga Road. The project seeks to improve travel times and reducing conflicts among the various modes of transport on the road and other vulnerable road users like pedestrians and cyclists.
Contractor: M/S SINOHYDRO
Commencement: 31st July, 2019
Expected Completion: 31st July, 2021
Physical Progress: 73.00%
6. DUALIZATION OF HO MAIN ROAD (SOKODE GBORGAME-CIVIC CENTRE)
The project is being executed to accommodate the anticipated high traffic volume that is expected within the volta Region in the near future. The project consists of the dualization of the main road into Ho from Sokode Gborgame and traffic management of existing roads within the city centre.
Contractor: M/S China Railway No. 5
Commencement: August, 2016
Expected Completion: December, 2021
Physical Progress: 56.00%
7. UPGRADING OF SPINTEX ROAD 1
The project is part of the Accra East Corridor and it seeks to create an alternative to the existing Spintex Road which has high volumes of traffic during peak hours. This project when completed would reduce travel time considerable within the Accra East Corridor.
Contractor: M/S Cymain Gh. Limited
Commencement: January, 2018
Expected Completion: December, 2021
Physical Progress: 27%